New Irrigation Tunnel Project Advances in Nebraska

New Irrigation Tunnel Project Advances in Nebraska


By Scout Nelson

Construction has officially begun on the replacement of Tunnel No. 2 along the Goshen/Gering-Fort Laramie main irrigation canal, a vital water delivery system serving western Nebraska and eastern Wyoming. The project comes more than seven years after the original tunnel collapsed, disrupting irrigation supplies for agricultural producers across the region.

Construction activities started on November 18 following a public launch event and open house hosted by the irrigation districts and Guy F. Atkinson Construction, LLC. The event gave community members, producers, and government officials an opportunity to learn about the project and view the specialized equipment that will be used during construction.

More than 100 people attended the launch event, including elected officials, representatives from the U.S. Bureau of Reclamation, local leaders, and area growers. Project representatives outlined the goals of the replacement effort and explained how modern tunneling technology will support the construction process.

A custom-built digger shield will play a central role in the project. The machine is designed to excavate approximately five feet of tunnel at a time, while removed material will be transported out of the tunnel and taken to a designated disposal site.

Construction crews will operate around the clock to keep the project on schedule. Three rotating crews will work continuously, ensuring steady progress toward completion.

As excavation continues, new tunnel lining segments will be delivered and installed inside the structure. Each tunnel section consists of six heavy components that will be bolted together and sealed to create a durable lining for long-term water delivery.

To strengthen the tunnel, crews will inject a specially formulated grout mixture around the outside of the new lining. This process helps fill gaps, improve stability, and enhance the tunnel's long-term durability.

The replacement of Tunnel No. 2 is expected to be completed by mid-May 2027. At the same time, preparations are underway for the future replacement of Tunnel No. 1, with construction scheduled to begin in fall 2027 and conclude in spring 2028.

The project marks an important milestone for irrigation districts and agricultural producers who depend on reliable water supplies. Once completed, the upgraded infrastructure will improve irrigation reliability and help support agricultural productivity throughout western Nebraska and eastern Wyoming.

Photo Credit: gettyimages-dmytro-diedov

Nebraska 2026 Crop Outlook Highlights Soybean Growth Nebraska 2026 Crop Outlook Highlights Soybean Growth

Categories: Nebraska, General

Subscribe to Farms.com newsletters

Crop News

Rural Lifestyle News

Livestock News

General News

Government & Policy News

National News

Back To Top